The proposed Selwyn Project is an open pit zinc-lead mine with a projected mine life of more than 10 years. The mine is being designed to process 35,000 tonnes per day (tpd) of ore which, after processing, is expected to result in 2,500 tpd of zinc and 600 tpd of lead concentrate. Once processed, the concentrate would be trucked to the Port of Stewart for export. We completed the Preliminary Economic Assessment (PEA) for the Selwyn Project in September 2014 and are working to complete the Prefeasibility Study (PFS) in 2015. These reports will include more detailed information about the specific components of the mine design. To keep up to date on the Selwyn Project, including future opportunities, sign up for our quarterly newsletter here.